Domestic chip factory 130 nm

    Somehow I read material about the unfinished Angstrem-T factory and decided to see if any work was actually underway on its construction, and if so, what was done. Since I still live close to the place of the proposed construction, to find out the situation, we went with a friend to the place of the proposed construction.

    Briefly about the background: Vnesheconombank (VEB) will become the owner of the Angstrem-T Zelenograd enterprise. The company was not able to pay the VEB loan received for the construction of a new microchip plant, and the bank decided to pick up a security deposit, which includes not only the shares and the plant’s land, but even its current equipment and the future 130 nm chip production line purchased from AMD. Information about this was published yesterday by the Vedomosti newspaper. Among the sources indicated is one of the partners of the Angstrom group and a source close to VEB. “In the future, the former shareholders will be able to buy the plant,” the publication adds.

    This is what official publicly available information writes.
    image


    The end date of construction is indicated in the 2nd quarter of 2011 as it is written in the article. Although there was already a deadline of 2009. So the end date may change.

    Quote: “At the same time, the Finance portal announced in August 2009, according to Angstrem’s top management, that a full-fledged production launch using 130 nm technology was planned for early 2011, without explaining the reason for the postponement. However, Dmitry Milovantsev, the general director of Angstrem-T, does not confirm the change of plans: “Angstrem-T shares were pledged to VEB. All decisions on the company require agreement with the bank . So far the plans have not changed, ”adds Finance.”

    Behind the fence there is a building that is not very similar to a factory if you are guided by a picture on a shield (There the color is blue, but in real life it is yellow and the configuration does not quite match). Maybe these are the features of the structure. To the left of the frame is the building of the customs terminal (TSW) of Angstrem OJSC. Builders do not see where they are?
    image

    Found the houses of the alleged builders of the shield exactly the same as hung on the fence, but no activity was found. I can say from myself that there used to be an iron hangar at this place. And to the left is the building of the Zelenograd customs.
    image

    On the territory of the proposed line, next to the building, there is a pit of unknown origin.
    image

    As the above source writes: “Angstrem-T tender portal provides some insight into the construction of the new plant: since the beginning of 2009, the plant has been carrying out various repairs of utilities - sewers and power networks, earthworks and“ drilling piles. ” Most tenders from May to September 2009 are listed as “pending”. As for the previous year 2008, there is no data on it. The latest tender announced by Angstrom-T involves preparing the M + W Zander building under construction for winter - “closing openings of various sizes,” the statement of work says. "

    M + W Zander the name already flickered on the shield. What kind of holes were closed remains behind the scenes) By the way, the tender site as well as the Angstrem-T site itself is now not available .
    image

    Further research, it was decided to turn off because they had already received a hat from the guard froze.

    Quote: “As Vedomosti wrote in August 2008,“ AMD equipment was paid for and is in stock in the Netherlands, says Angstrem deputy general director Evgeny Kolosov, there are no warehouses in Russia where you can store it. In autumn, as soon as “clean rooms” are installed at the plant under construction in Zelenograd, they will bring him. ” “Almost nothing has been done since then, the construction has not advanced a single step.”

    By the way, the 180 nm chip production line was purchased in 2007 at the Mikron plant . But still not launched .

    Instead of a conclusion, the described places are located 600 meters from the shooting location of one ofepisodes of the film "Adolescents in the Universe" once the former embodiment of progress in the USSR.image