    Imagine that in a restaurant you were offered to try a new sauce for your favorite dish, noting that it becomes twice as tasty. In this case, you will have nothing left to do but to do it. After all, it is not possible to define otherwise why the waiter rated his subjective feelings as “twice as tasty” and not, for example, at three. When it comes to spending on IT infrastructure, few people are willing to rely on someone else's feelings or intuition in this matter. To choose the “twice as tasty option” you will need to find a reliable and reliable method for evaluating economic efficiency.

    This calculation is especially important if you need to convince the management, including the financial director, of the correctness of your decision.

    The purpose of this article is to understand the TCO methodology for different options for obtaining the right to use the IT infrastructure and carry out the appropriate calculations in order to identify the most cost-effective alternative.

    RESULTS OF RESEARCH ARE (UPD)

    • understanding of the need to take into account the level of fault tolerance of IT systems as a key feature “to compare apples to apples”;
    • calculation of the total cost of ownership of the IT infrastructure for two patterns of use: the ERP system and the web resources of the sports portal;
    • a comparative analysis of the total cost of owning your own IT infrastructure and for renting a cloud;
    • factor analysis of savings on the benefits of cloud technologies and identifying the most favorable patterns of cloud use.

    What is TCO?


    The total cost of ownership or life cycle cost ( Total Cost of Ownership (TCO )) is the total amount of target costs that the owner has to bear from the moment of the beginning of the realization to the state of ownership until the owner leaves and fulfills the full amount of obligations, associated with possession.

    The TCO method was developed in the late 1980s by the Gartner Group to calculate the financial costs of owning computers on the Wintel platform (MS Windows + Intel). It was improved in 1994 by Interpose and reworked into a full-blown model for analyzing the financial side of using information technology. With this calculation of TCO, the costs of creating a hardware platform, purchasing software licenses, IT labor costs, and so on are the so-called “direct” or “budget” expenses. But there are still implicit financial investments in the maintenance of its IT infrastructure, costs and losses associated with its operation, and so on. Moreover, the authors of the methodology TCO argue that such costs constitute the bulk of the total cost of ownership of the IT infrastructure.

    That is, in fact, enterprises spend much more money on the maintenance of their “iron” than they suppose . Why is this happening and is it possible to optimize the costs of your own IT infrastructure?

    It is these goals that the TCO technique pursues. But in order to understand how you can manage maintenance costs, you must first clarify how they are calculated [ 1 ].

    To date, there is no universal methodology for determining (calculating) the total cost of ownership, since, depending on the object of ownership, the characteristics of ownership, cost structure and principles for their determination may vary significantly. However, there are common approaches to determining cost at all stages of the life cycle.A key principle implemented in the development of methods for determining the total cost of ownership is a systematic approach .

    For an integrated estimate of the cost of ownership, simplified methods for calculating the TCO can be applied, identifying, first of all, the cost structure, and giving an idea of ​​the likely losses in the process of ownership.

    Thus, it is necessary to make an individual calculation of the TCO for each case and, despite the fact that most of the costs can be determined in advance, or predicted with high accuracy, some costs are probabilistic in nature, which entails the risk of significant deviations of the actual costs from the estimated (estimated ).

    How we recommend considering the total cost of ownership of the IT infrastructure and why


    TCO or the estimate of total cost of ownership due to its probabilistic nature is rather not important in and of itself, as it is applicable for comparing the costs of alternative ways of obtaining the necessary computing resources.

    The most popular alternative to buying your own hardware and virtualization software is to rent a complete IT infrastructure in the cloud using the IaaS model ( English Infrastructure as a Service - Infrastructure as a Service).

    There is nothing difficult in calculating the TCO of the cloud: we take and add all payments to the provider for the period. It is much more difficult to calculate total expenses for our own infrastructure, and we will discuss this in detail later.

    Have you already managed to carry out the necessary calculations? Now you can compare? Yes, if you did it right.

    Do not forget about an important characteristic of the created IT infrastructure as a system - the level of fault tolerance or uninterrupted operation of its process. It is clear that the higher the level of accessibility of services, the better: the work of office employees does not stand idle because of a server automation error in the accounting system, and buyers do not leave the online store because of the “error 503”.

    In general, a business would like to get 99.99% availability. However, creating a solution of this level will require significant investment. For example, a solution based on two storage systems with synchronous mirroring, located in a pair of geographically distant data centers, has such a level of fault tolerance. Not surprisingly, the cost of such a service will be 2 times higher.

    Does everybody need such a solution? Of course not. If we are talking about the expected level of availability of 99.95% or 4 hours 23 minutes of downtime per year, we are expected to lose only 0.04% of uptime to the solution, which is 2 times more expensive. In a common year, there are 8,760 hours, which means that if there are no natural cataclysms from which only a disaster-proof solution would save us, we add only 3.5 hours per year to the uptime of the IT infrastructure per year, investing significant funds.

    So, we come to the question of how much a minute of downtime costs for your business and what level of fault tolerance you need. Are you familiar with the scary phrase “cost of downtime”?



    According to a survey conducted by the Ponemon Institute in 2014, the average cost per minute of inactivity is $ 7,900, compared with $ 5,600 per minute four years earlier. Although these numbers may look catastrophic, they can easily be discarded as relevant to only a few of the largest companies in the United States.

    For the e-commerce giant, such as Amazon, the numbers are even higher. Losses of up to $ 66,240 per minute of service downtime have been reported. At this time, a minute of downtime for small businesses is much cheaper, the relative cost is still significant. Surprisingly, efforts to measure and manage these risks have only recently become a priority for business. As a result, it is easy to make a mistake by ignoring the danger of IT infrastructure downtime, and not try to assess its impact on the results of operations.

    How can you estimate losses during downtime if you are a small or medium business? Not surprisingly, the corresponding loss math is less impressive. But don't let the numbers fool you. Even a niche retail store with a relatively modest income will experience the “pain" of downtime. Let's look at the list of factors that together form the total cost of losses:

    Direct sales revenue loss




    This may seem trivial, but assuming revenue is generated online or strictly dependent on IT, you simply need to divide the annual sales amount by 525,600 (60 min. X 24 hours x 365 days) to determine the average cost of downtime per minute. Thus, the loss formula can look something like this:



    Where t denotes the number of minutes your IT infrastructure is idle.

    Cost of loss in employee productivity


    Estimated cost of time, workers who are affected by a simple and who can not work as usual.



    Where W denotes the average hourly wage per employee, and N denotes the number of employees affected by downtime. t in this case is expressed in hours.

    IT infrastructure repair cost


    The cost of IT staff time restoring your system from a backup or replacing failed hardware.



    Where N_IT is the number of employees involved in IT recovery operations instead of other business-friendly activities, and t 'is the time needed to correct the problems of all affected systems and return them to normal.

    Projected loss of income due to reduced customer loyalty


    For simplicity, let's assume that the business in question is not widely reported by the media, so we calculate the projected lost income based on the loss of possible repeat sales.



    Where r denotes the average rate (percentage) of the decrease in repeat sales, and D is the revenue from repeat sales for the year.

    Projected loss of income due to reputation damage


    Lost sales to customers exploring the market looking for a better deal or collecting recommendations.



    Where r 'denotes the percentage of sales decline associated with customers who come from sites with reviews to compare products / services and social networks.

    Thus, the formula for total cost of idle time (TCoDT, total cost of downtime) might look like this:



    Where sales are, employees are, time is fixed. IT, U_loyal, U_reputz respectively mean lost income, the cost of loss due to reduced employee productivity, the cost of restoring IT infrastructure, the projected loss of repeat sales and the projected loss due to damage to reputation.

    As an example, consider an online store with 50 million rubles in sales and 15 employees in the state. Hourly 5708 rubles or a little more than 95 rubles per minute are direct losses of income.

    What is the expected duration of a simple year for the company?

    Much depends on how the IT system of this business is organized. Well-studied and typical objects are public data centers. The Uptime Institute has created a layered classification system for the systematic evaluation of various facilities and equipment of data centers in terms of potential infrastructure performance or uptime capability. The system consists of four levels, each level includes the requirements of the lower levels (Tier):

    • Tier I: Basic Capacity - base potential, infrastructure without reservation;
    • Tier II: Redundant Capacity Components - duplication of critical components, redundant infrastructure;
    • Tier III: Concurrently Maintainable - infrastructure with the possibility of parallel repair / maintenance without stopping work;
    • Tier IV: Fault Tolerant - fault tolerant infrastructure.



    Although the Uptime Institute removed the information on “expected in a simple year” from Tier Standard in 2009 [ 2 , 3 ], we can draw conclusions that, by publishing these data, data center operation experts previously reported information on failures and to the conclusion that the basic infrastructure without redundancy expectedly works flawlessly 99.671% per year or idle due to accidents 28.8 hours.

    Often, companies or their remote branches, where servers are located locally, there are no dedicated rooms for server and switching nodes, racks are not protected, there is no access control, no redundancy, cable organization is low, and specialized cooling and fire extinguishing systems are not at all are thinking. And this is not even Tier 1 with expected downtime for more than a day. A fire in such premises is more likely, and the resulting downtime can last a month and lead to bankruptcy.


    The "deplorable" state of the server can cause major accidents

    It should be noted here that the entire IT system of an organization is a bundle of support systems (electricity, cooling, security, etc.), communication channels, the server hardware, network equipment and data storage systems, system-wide and application software. In such a multi-level system, the total expected uptime is the product of the fault tolerance levels of each component or, for



    example, Availability = 99.671% (local data center without redundancy) × 99.671% (IT equipment without redundancy) = 99.343% or about 2.5 days of expected idle time if failures are caused for different reasons and at different times.

    Suppose you have a fairly well-organized activity, and a simple IT infrastructure lasts no more than nine hours a year, a little less than three nines (99.9%). This means that all workers affected by the failure (presumably 2/3) could not work normally, at least during this period of time. If we take the average hourly wage with taxes and fees of 500 rubles, it will cost the company 45,000 rubles because of the loss of productivity.

    Logically, the IT team will spend some more time figuring out what went wrong so that it can prevent repeated failures. Imagine that your IT geniuses need 50 hours (800 rubles / hour) to fix everything. This time workers could spend on solving the problems of developing your business. Even if you allocate only one employee for this problem, these are additional 40,000 rubles, which should be included in the cost of IT restoration.

    Finally, not only customers that you have lost, “sending” to one of your competitors, will never return, new customers are less likely to make purchases from you on the advice of partners or on recommendations and reviews on websites to compare products and services.

    So, it’s estimated that we’ll add a loss of 50,000 rubles to take into account an additional 1% of the projected losses on repeat sales for the year and 35,000 rubles for a 2% loss of sales from reviews and recommendations caused by downtime. An unpleasant picture emerges, but let's add it all:
    Loss of sales
    51 372
    Performance loss
    45,000
    IT recovery cost
    40,000
    Losses on repeat sales
    50,000
    Sales loss by review
    35,000
    Total cost of IT infrastructure downtime
    221 372 rubles.
    It quickly becomes clear why there is a significant gap in how small businesses and corporations approach the assessment of losses from downtime - from measuring the consequences to the long-standing need for building response and recovery procedures.

    According to a survey of representatives of big business in the United States, 37% of organizations estimate a day of downtime at a loss of more than 10,000 US dollars, which echoes 38% of respondents who report annual income of more than 10 million dollars. Thus, although the numbers for small and medium businesses are significantly lower than actual losses for corporate downtime, it is also clear that even small businesses that rely on modern technology should be serious about the problem of uptime, given their scale.

    With a longer idle time, which your customers have to endure, with each additional hour the probable losses on repeat sales and due to negative feedback grow faster. Thus, an accident in the IT infrastructure can become not only the cause of losses, but also deprive the company of financial stability.

    Article 4 of the Law of July 24, 2007 No. 209-ФЗ and the Resolution of the Government of the Russian Federation of April 4, 2016 No. 265 inform us about the income and number of employees who are criteria for a business to receive a certain legal status.
    The limit value of the average number of employees for the previous calendar year
    Revenues for the year according to the rules of tax accounting will not exceed:

    15 people for micro enterprises;


    16–100 people - for small enterprises;


    101–250 people - for medium-sized enterprises


    120 million rubles. - for microenterprises;


    800 million rubles. - for small enterprises;


    2000 million rubles - for medium-sized enterprises


    Thus, even the example of a microenterprise we examined with 15 employees and 50 million rubles of annual income shows that a small simple 0.1% per year brings serious losses to the business, which can be a significant percentage of annual profits. That is why small and medium enterprises need to implement an IT system with a level of reliability close to 99.95%. This choice is the "golden mean" between the additional costs of disaster-proof solutions and the minimization of losses from downtime of less reliable systems.

    The calculations above describe the work that CIOs must do as a starting point for choosing alternatives. Having determined your risk appetite and the allowable loss from IT system downtime, you need to design all elements of the system based on the overall planned level of process continuity. The result should be consistent with the tactical and strategic business goals, and not to limit or be an obstacle to their achievement.

    As part of this work, we will designate the target level of IT continuity at 99.95% per year. Next, we turn to the calculation of the total cost of ownership for different models of using the IT infrastructure only with a given level of expected fault tolerance.

    TCO on-premise solutions


    To add a bit of versatility to our example, we will talk about the same hardware configuration, but for two patterns of its use. Our examples will be

    • ERP for 350 users
    • Popular Sports Portal Website

    We will calculate TCO for periods of 3 and 5 years.

    Purchase of own equipment


    To perform calculations for these tasks, the following hardware configuration will be used. Focusing on the average market prices for high-end server hardware and mid-range storage systems, we get the expected costs:
    Equipment
    Price
    3 + 1 Servers: CPU Xeon® E5 4 core 2,6GHz, RAM 64 Gb, 2x10Gb
    1 500 000 rubles
    Storage SAS with a total volume of 11 TB (operational data up to 1TB RAID1, other historical RAID6)
    2 300 000 rubles
    1 + 1 Switches
    200 000 rubles
    Why mid-range storage? The average level is already serious systems in which protection against most failure scenarios is thought out, a higher maintenance level (including the possibility of remote monitoring by a service center and replacement of on-site disks under warranty).

    The reliability of such systems is calculated in the number of "nines", of the order, for example, 99.999% of the declared uninterrupted work time per year. Most repair operations and many upgrades for hardware and software (alas, not all) can be done without disruption. And we remember that we stand the system with a general fault tolerance of not less than 99.95%. Thus, we save without buying high-end storage systems, which are several times more expensive, but do not lose in uninterrupted operation.

    The server equipment is chosen high-end, since it is for enterprise-level servers that a variety of monitoring and management functions are implemented, fault tolerance and good scalability are ensured.

    So, we received the first capital expenditure on the purchase of equipment. They amounted to 3 000 000 rubles.

    This could be finished with equipment costs, but since we expect TCO for 5 years, and the standard warranty often ends after 3 years, we add the cost of extending warranty service for 2 years. Since the cost of extending the warranty varies for each vendor, we estimate this cost as 20% of the cost of equipment for 2 years or 600,000 rubles in our case. The calculation of the percentage of the cost of post-warranty service was carried out using the example of HPE technology [ 4 ].

    Place for placing: data center or on-premise


    Next we need to decide where we will place our equipment. Well, if you have an excellent server that is crammed with modern systems, but what if you build it from scratch? How much will such a project cost?

    In order to somehow estimate the costs, we turned to the study “Estimated Total Cost of Ownership of a Data Processing Center” by L.А. Pirogov, V.I. Grekul and B.E. Poklonova [ 5]. Based on the analysis of the construction market of commercial data centers, the authors come to a confidence interval from 59 to 88 thousand US dollars according to the results of regression modeling of capital expenditures for the construction of 1 rack in the data center in Moscow. Thus, even saving on scale, in order to get a reliable platform for equipment placement, which can correspond to the expected equipment downtime of not less than 99.95%, it is necessary to spend about 4.5 million rubles only for construction and equipment without taking into account operating expenses. Of course, the option of such non-core costs disappears for almost all organizations.

    The logical option is to place servers or rent a rack in a commercial data center, the so-called Colocation. The market for commercial data centers is well developed, this approach to the placement of equipment has become generally accepted for reasons of obvious economic feasibility.

    Placement of 6 units in the Tier III data center (backup of power supply systems, cooling, telecom infrastructure and fire extinguishing systems, the ability to repair systems without stopping the server room) in Moscow at average market prices, taking into account the additional to the basic electricity consumption tariffs and a guaranteed channel per month.

    If you decide to place the equipment in your own server room, then you should take into account the total power consumption of your data center (server) - this is the power consumption of IT equipment plus the consumption of everything that supports its work, namely:

    • power supply systems, including UPS, switchgear, generators, batteries; This includes losses in the distribution of external power to IT equipment;
    • components of cooling systems: chillers, cooling towers, pumps, ventilation systems and air conditioners of engine rooms, humidifiers, etc .;
    • other loads, for example, data center lighting.

    To determine the energy efficiency in the industry, it is customary to use the PUE indicator. The PUE (Power Usage Effectiveness) parameter is defined as the ratio of the energy requirements of the IT infrastructure to the total energy supplied to the data center. The ideal PUE value is equal to one, in this case all the energy used by the site goes to support the operation of the servers. In practice, this situation is impossible, the minimum PUE values ​​reach around 1.1-1.15, the organization of work using the “best methods” gives an average of 1.6, and the average PUE for TIER III data centers is 1 in the world , 98.


    Source: APC by Schneider Electric, 2010

    Thus, if your IT equipment has a rated power of 4 kW, then with a PUE of 2, you will need 8 kWh. If the server works 24 hours a day, about 5,800 kW will be released within a month, which at a rate of 5 rubles per kW will cost 29,000 rubles. From this it becomes clear that in the price of placement in a commercial data center a significant part of the cost is occupied by electricity, and other expenses are distributed to numerous tenants who pay less than if they would have implemented such conditions in the enterprise locally.

    We fix the costs of 40,000 rubles per month for the placement of equipment in a commercial data center as an economically optimal choice and in the future we will use only this option for calculations.

    Software costs


    Why we will consider an example using virtualization? Virtualization can increase the adaptability, flexibility and scalability of the IT environment and significantly reduce costs. Virtualization accelerates the deployment of workloads, increases their productivity and availability, and also provides an opportunity to automate processes, as a result of which the company's IT infrastructure becomes more manageable and economical. Additional benefits include the following:

    • reduced capital and operating costs;
    • minimizing or eliminating downtime;
    • increased responsiveness, adaptability and overall performance of IT staff;
    • accelerate the initialization of applications and resources;
    • business continuity and disaster recovery;
    • simplified data center management;
    • creation of fully software data center.

    IT departments face the limitations of modern x86 servers, which are designed to run only one operating system and one application at a time. As a result, even in small data centers, a large number of servers have to be deployed, each with a load of only 5–15%. It is ineffective from any point of view [ 6 ].

    In virtualization, software is used to simulate the availability of equipment and create a virtual computer system. Because of this, business units can run multiple virtual systems, as well as multiple operating systems and applications on a single server. This approach provides economies of scale and efficiency.

    Can I use free virtualization platforms?

    In case you do NOT need a massive deployment of virtual servers in your organization, constant monitoring of the performance of physical servers under varying load, and a high degree of availability, you can use virtual machines based on free platforms to maintain the organization’s internal servers [ 7 ]. With the increase in the number of virtual servers and their high degree of consolidation on physical platforms, the use of powerful tools to manage and maintain the virtual infrastructure is required.Depending on whether you need to use different systems and storage networks, such as the Storage Area Network (SAN), backup and disaster recovery tools, and live migration of running virtual machines to other equipment, you may not have enough free Virtualization platforms, however, should be noted that free platforms are constantly updated and acquire new functions, which expands the scope of their use.

    Another important point is technical support. Free virtualization platforms exist either within the framework of the Open Source community, where many enthusiasts are engaged in finalizing the product and its support, or are supported by the platform vendor. The first option involves the active participation of users in the development of the product, making error reports by them and does not guarantee solving your problems when using the platform, in the second case, more often than not, technical support is not provided at all. Therefore, the qualifications of personnel deploying free platforms should be at a high level.

    Thus, we come to the conclusion that for a corporate use case, for example, an ERP system, we will need paid virtualization software with advanced functionality. Leading positions in the market occupy VMware. All Fortune 500 companies choose the VMware infrastructure platform, which has helped customers save tens of billions of dollars.

    An important factor in choosing a VMware software platform is the lowest total cost of ownership compared to competing solutions. You can independently use the calculators of total cost of ownership and return on investment for comparison with alternatives, such as solutions from Microsoft and traditional IT infrastructure [ 8 ].

    Since we initially decided that we will consider two use cases, then for a case with a sports portal, we agree that free, open-source software solutions will be used, and in the case of ERP - licensed software from VMware.



    Total for virtualization software - 1.2 million rubles. The annual cost of technical support and access to update products - 334 thousand rubles.

    Add to this the license for software for storage medium level - 100 thousand rubles.

    Staff costs


    While actual personnel costs to support the stable operation of the IT infrastructure typically consist of several different people’s salaries, for simplicity, we will use a simple ratio between the number of servers and the number of people that AWS derived for use in their cost models. Let's call this the “server-to-admin” ratio.

    Based on customer discussions, AWS found that a 50-to-1 ratio is a good average derived from a range that is common to many companies. We recommend adjusting this assumption based on your own research and experience and include in the staff costs all the people involved in creating and managing your physical data center, and not just the people who install and administer the servers. The actual relationship between people and servers can vary greatly, since it depends on a number of factors, such as the complexity of the automation, the tools used, the choice in favor of a virtualized or non-virtualized environment.

    Since we are talking about some abstract employee who will have different specializations corresponding to current tasks, we will use the median monthly salary of an IT specialist for the first half of 2018 from the My Circle service report [ 9 ].

    According to the survey, it amounts to 90,000 rubles per person after deducting all taxes and fees. Adding another 50% to payments to the Pension Fund, the MHIF, the Social Insurance Fund and personal income tax, we get 135,000 rubles. This is the cost of one IT specialist who is 100% loaded with working with IT infrastructure, the creation of which we describe in our case.

    Since we have 4 servers and 1 storage system, applying “server-to-admin” equal to 50 to 1, we get about 10% of the cost of working time of one “universal” employee or 13.5 thousand rubles of expenses per month.

    Total costs for own infrastructure


    Capex (capital expense or capital expenditure) means capital expenditure or expenses. These costs are usually one-time (irregular), directed by the company to purchase non-current assets, their modernization and reconstruction.



    Opex (English operating expense, operating expenditure - operating costs) - the costs incurred by the company in the course of its current activities to ensure operation. Such expenses are also called costs of the current period.



    The total TCO of such an infrastructure will amount to 7,331,498 rubles over 3 years, and 9,884,214 rubles over 5 years.



    Thus, the initial investment in software and equipment in the future 5 years increase by more than 2 times. By themselves, the 4.8 millions needed to run this infrastructure also contain risks.

    First, the price of a mistake. If we are not talking about a stable enterprise with a well-predicted need for computing power, but consider a start-up with a new service that is trying to conquer the market, all the initial investment can be wasted. Yes, of course, the purchased equipment can be sold. However, such transactions are carried out with a large discount, and the search for a buyer can last for months.

    Secondly, the value of money.Often such projects are implemented with the involvement of credit funds. Having received a loan of 4 million rubles with an interest rate near the minimum threshold for legal entities. persons at 12% per annum, the amount of interest for 3 years will be 783 thousand rubles.

    We will not add these optional costs to our TCO calculation , however, when you do an analysis of your case, you must take into account the conditions for receiving money by your business and add the corresponding costs.

    It turns out, owning "their own iron" is quite expensive. An alternative option is the use of cloud services. Let's move on to the comparison.

    Calculate tco clouds


    Since we cannot talk about the costs of the cloud without choosing a specific provider, we will do our own TCO analysis.

    Since its foundation in 2009, the Cloud4Y corporate cloud provider has been focused on the needs and high business requirements for IT services. We offer software-configured data centers (vDC) based on VMware vSphere cluster solutions managed by the VMware vCloud Director self-service portal.

    In addition to the IaaS model (infrastructure as a service), we have developed and successfully provide clients with many relevant and popular SaaS products (1C in the cloud, remote desktops, corporate mail, antispam, and more).

    Used VMware technology stack (vSphere, NSX, vCloud Director), reliable hardware(HP blade servers, all-flash storage systems, Cisco and Juniper switches) located in the TIER 3 secure data center network, connected by a high availability optical ring with duplicate communication channels, ensure proper quality of services and fault tolerance required for enterprise clients.


    Cloud4Y provides full hardware redundancy of server and network equipment. Backup is carried out in a geographically remote data center. VMware cluster options are implemented by default: vMotion “live migration”, automatic transfer of a virtual machine to a backup host in case of VMware HA (High availability) failure, load balancing between VMware DRS hosts.

    If you need to reduce downtime to a minimum time, it is possible to use the technology of VMware Fault Tolerance. The main idea of ​​the option can be described as creating a synchronous replica of a virtual machine on another server and instantly switching to it when the primary host fails.

    Technical support is provided in the mode of 24 * 7 * 365. The support is divided into three lines:

    • The first line of technical support deals with issues of accessibility and technical issues up to the OS level inclusive, gets tickets and advises clients. In the case of requests that do not affect the data, and do not relate to finance, customer issues can be resolved by any of the available methods.
    • The second line of technical support deals with the level of hypervisors and operating systems, customization of client software, customization, log analysis, integration issues and deep support for client information systems.
    • The third line of support solves problems globally at the network level, at the level of data storage systems, and is responsible for the architecture and availability in general.

    We see that all components of the Cloud4Y cloud are designed to ensure the maximum level of business continuity. This suggests a total expected system availability level of 99.982% per year. Not a single element of the system, be it a network, equipment, site or virtualization platform, is a weak link.

    The availability level is 99.982% higher than the minimum level we planned. So, let's proceed to the calculation of TCO in the cloud and find out if we can get services without a premium for increased fault tolerance.

    An alternative nominal configuration in the cloud will be 32 vCPU, 256 Gb RAM and 11 Tb Medium SAS (4400 IOPS). When calculating on the calculator on the site, we get 250,824 rubles a month and a discount offer. Depending on the project, the discount will be different, but we plan a possible discount at the level of 20%, which ultimately will give us 2,407,910 rubles a year, 7.22 million over 3 years and 12 million rubles over 5 years.

    At this stage, the cloud solution loses the creation of its own IT infrastructure, but do not rush to conclusions.

    Reservation


    First, the hardware reservation is already provided by the provider, in case of failure, you will be allocated another host from the provider resource pool. This means an alternative power configuration is 24 vCPU, 196 Gb RAM and 1 Tb Medium SAS and 10 Tb Low. We receive already 187 793 rubles a month or 150 234 rubles. with discount.

    With this adjustment, we are already at a lower total cost than our own architecture. We talked about 7.3 million rubles for 3 years, and 9.9 million rubles for 5 years for our own "iron". At this stage, the cloud is already cheaper - 5.4 and 9 million rubles, respectively.

    Elasticity


    An important advantage of cloud computing is elasticity (rapid elasticity). Resources can be quickly allocated and released, in some cases automatically, for rapid scaling, commensurate with demand. For the consumer, the possibilities of providing resources are seen as unlimited, that is, they can be assigned in any quantity and at any time.

    In other words, if you need 30 CPUs, then you simply rent 30 CPUs in the cloud. But, if you build your own resources, then you definitely will not create exactly 30. Imagine that you are the CIO of the sports web portal, and are preparing the computing power for the World Cup. In this case, you should be ready to peak visits during this period, and the key question for you is what resources will be sufficient. If there are too few of them to plan, then there will not be enough of them during major sports events, and if there are too many, they will stand idle the rest of the time.

    In the beginning, we talked about two usage patterns. In the case of the ERP system, we will increase the amount of resources used from 2/3 in the first three years, to full utilization (payload) for 4 and 5 years. For the resources of the sports portal, we will foresee two peaks of almost 100% downloads per year lasting 1 month each, the rest of the time resources will be used only by 40%.

    image

    It is the high utilization of resources and effective management that allows cloud providers to earn from their business. How does this help save tenants?

    We proceed to the calculations.

    ERP scenario: 2/3 of resource utilization (121 thousand rubles / month) in the first three years will cost 4,356 million rubles, and all 5 years, taking into account the growth - 7.961 million rubles.

    Sports portal:1/6 utilization to 100% of the maximum quantity of resources, and 5/6 - 40% utilization. Storage resources - growth from 40% to 90% for 5 years.

    In the graph below, you can see how costs are rising over 5 years and how user portal peaks in the portal affect cloud infrastructure costs.

    image

    Using resources as needed, you can reduce costs to 2.494 million rubles. for three years and 4,543 million rubles. for 5 years.

    So, we are finally ready to compare the TCO of the cloud solution and the purchase of our own hardware.



    According to our calculations, the cloud for the corporate use scenario is cheaper by 1.9 million rubles or 19.5% cheaper in 5 years and 40.5% cheaper in the future 3 years.

    We have added options using free virtualization software and with renting physical servers in the data center with our license, but even they lose to the cloud for 3 years. When comparing a 5-year TCO, these options turn out to be “more profitable”, but they imply a decrease in manageability, resiliency and flexibility. Such options are poorly applicable for corporate IT, in the scenario of use for the sports portal these options are losing to the cloud even in TCO-5 years.

    Cost of money


    At the very least, the money saved could have been used by the business for other projects, and therefore it would be profitable. Taking a return on investment of 10% per year, we can talk

    • about profits from 1.7 million rubles from free cash flow (the difference between the costs of on-premise and cloud monthly) and the saved 1.9 million over 5 years in the ERP scenario
    • and 2.5 million "unfused" profits for the sports portal plus the saved 5.3 million rubles.

    Pay as you go


    Cloud4Y provides the “Pay as you go” payment model for each type of resource separately. This approach makes it possible to pay for resources upon consumption. We use today just as many cores and RAM as needed. It should be noted that in all cases, the CPU and RAM fees are taken only for the “on” time, when you are not using the virtual machine - the fee is not charged. But the storage will have to be paid regardless of whether the machine is turned on or off - the fee is taken until the disk has data, if the disk is clean, the fee is not charged.

    On the site, you can find a service cost calculator, but it is worth noting that it works based on the assumption of using the VM in 24x7x30 mode. Using a VM in 12x5x30 mode, the cost of the service for you may be lower by more than 50-60%. Such a pattern of resource utilization is typical, for example, of the infrastructure of virtual remote desktops or “cloud office”. When organization employees are not working, the virtual machines with their desktops are turned off, and savings begin. We did not consider such a use case versus TCO, but it is logical and tested in practice that the cloud bypasses other alternatives in this case.

    findings


    image

    The graph clearly shows that during the entire 5-year life cycle of the IT infrastructure, Cloud4Y benefits from the purchase of its own hardware. Outside of this period, servers are likely to become morally obsolete and it will be necessary to purchase new ones. The provider itself is also responsible for updating the equipment in the cloud. Thus, consideration of a longer period will not change the situation with the economic viability of the cloud.

    There are options when the cloud will be less profitable. Basically, these are cases with the presence of already acquired and idle equipment or the purchase of servers in order to slightly increase the already existing and effectively used resources. It is also possible to conclude that cloud services are more significant in scenarios with abrupt or unpredictable capacity utilization.

    In order to get advice and calculate TCO in the cloud for the case of your organization, please contact any Cloud4Y manager in the way that is most convenient for you.

    Sources
    1. Optimization of IT costs // Internet-project “Corporate Management”. URL: www.cfin.ru/itm/tco.shtml (appeal date 09/20/2018)
    2. Официальный сайт Uptime Institute. URL: ru.uptimeinstitute.com (дата обращения: 19.09.2018)
    3. Мифы и заблуждения относительно Tier-системы сертификации Uptime Institute // Сайт Cloud4Y. URL: www.cloud4y.ru/about/news/Myths-and-Misconceptions-Regarding-the-Uptime-Institute%E2%80%99s-Tier-Certification-System (дата обращения: 19.09.2018)
    4. Сайт Hewlett Packard Enterprise Support Services Central. URL: ssc.hpe.com/portal/site/ssc/?action=determineNodeContents&nodeId=30749 (дата обращения: 24.09.2018, выбранная длительность — 2 года)
    5. «Оценка совокупной стоимости владения центром обработки данных». URL: bijournal.hse.ru/data/2016/08/11/1118257058/%D0%9F%D0%B8%D1%80%D0%BE%D0%B3%D0%BE%D0%B2%D0%B0%20%D0%93%D1%80%D0%B5%D0%BA%D1%83%D0%BB%20%D0%9F%D0%BE%D0%BA%D0%BB%D0%BE%D0%BD%D0%BE%D0%B2%20%D0%A0%D0%A3%D0%A1.pdf (дата обращения: 24.09.2018)
    6. Принципы виртуализации // Официальный сайт VMware. URL: www.vmware.com/ru/solutions/virtualization.html (дата обращения: 25.09.2018)
    7. Бесплатные серверные платформы виртуализации. URL: www.ixbt.com/cm/virtualization-servers-free.shtml (дата обращения: 25.09.2018)
    8. VMware TCO Comparison Calculator. URL: tco.vmware.com/tcocalculator (дата обращения: 24.09.2018)
    9. Зарплаты ИТ-специалистов на середину 2018 года // Блог сервиса «Мой круг» на Хабр URL: habr.com/company/moikrug/blog/420391 (дата обращения: 20.09.2018)


    Free Download link White Paper: Calculate TCO Cloud vs Purchase Servers (.pdf)